English term
special attendance
English to Arabic
Law/Patents
Law (general)
these items will be procured directly by the Employer, the Tenderer to allow for special attendance, provisions, builder's works, coordination, whatsoever as per the Tender/Contract documents and the relevant conditions
Proposed translations
(Arabic)
3 +2 | مقاول باطن متخصص | HATEM EL HADARY |
4 +1 | خدمة خاصة | Lamine Boukabour |
5 | إحضار وتهيئة الموقع لمقاول باطن متخصص | Reem Mansour |
4 | الحضور الخاص | Mahmoud Ibrahim |
4 | متطلبات مقاول الباطن | Assem AlKhallouf |
Proposed translations
+2
8 mins
Selected
مقاول باطن متخصص
مقاول باطن متخصص
--------------------------------------------------
Note added at 9 mins (2021-07-03 10:05:49 GMT)
--------------------------------------------------
مقاول متخصص في أعمال المقاولة من الباطن
--------------------------------------------------
Note added at 20 mins (2021-07-03 10:16:48 GMT)
--------------------------------------------------
https://www.proz.com/kudoz/english-to-arabic/law-contracts/2...
--------------------------------------------------
Note added at 9 mins (2021-07-03 10:05:49 GMT)
--------------------------------------------------
مقاول متخصص في أعمال المقاولة من الباطن
--------------------------------------------------
Note added at 20 mins (2021-07-03 10:16:48 GMT)
--------------------------------------------------
https://www.proz.com/kudoz/english-to-arabic/law-contracts/2...
4 KudoZ points awarded for this answer.
Comment: "Selected automatically based on peer agreement."
7 mins
الحضور الخاص
Special attendance is specific to a particular supplier or sub-contractor if it requests that it is provided by the main contractor, such as: Special hoists. Builders work such as a concrete plinth
+1
1 hr
خدمة خاصة
خدمة/خدمات خاصة.
Special attendance: It is any item/service the sub-contractor requests to be provided by the main contractor in order to complete his works. e.g. main contractor obtains a quotation from a sub-contractor to install external signage to a building; however the quotation excludes cradles and mobile cranes required for installation and completion of the works. 'The Cradle' and 'The Mobile Crane' constitue the main contractor's special attendance (which could have been priced/unpriced during tender stage as per the Client's requirements).
Special attendance: It is any item/service the sub-contractor requests to be provided by the main contractor in order to complete his works. e.g. main contractor obtains a quotation from a sub-contractor to install external signage to a building; however the quotation excludes cradles and mobile cranes required for installation and completion of the works. 'The Cradle' and 'The Mobile Crane' constitue the main contractor's special attendance (which could have been priced/unpriced during tender stage as per the Client's requirements).
Example sentence:
The Cradle' and 'The Mobile Crane' constitue the main contractor's special attendance (which could have been priced/unpriced during tender stage as per the Client's requirements).
Peer comment(s):
agree |
Z-Translations Translator
: https://www.proz.com/kudoz/english-to-arabic/law-contracts/6...
9 days
|
1 hr
إحضار وتهيئة الموقع لمقاول باطن متخصص
If the scope of works requires (in some stages of contract) to bring a specialized subcontractor to do specific works, (piping coating as in the case of constructing a pumping station contract ), the Main Contractor has to provide the site, accommodation and other expenses to such Specializes Subcontractor. This is called attendance cost.
--------------------------------------------------
Note added at 1 hr (2021-07-03 11:20:19 GMT)
--------------------------------------------------
https://civilengineeringlectures.com/nominated-subcontractor...
--------------------------------------------------
Note added at 1 hr (2021-07-03 11:20:19 GMT)
--------------------------------------------------
https://civilengineeringlectures.com/nominated-subcontractor...
9 hrs
متطلبات مقاول الباطن
المتطلبات الإضافية للمتعاقدين من الباطن
"Additional requirements should be described as 'Special attendance'."
https://tinyurl.com/bnm3bkwv
"The Subcontractor will be responsible for all other attendances with exception of special attendance."
https://tinyurl.com/4e9rbnv5
"Special attendance is specific to a particular supplier or sub-contractor if it requests that it is provided by the main contractor."
https://tinyurl.com/8wmha6tv
"8.0 SPECIAL ATTENDANCE ON N/S SUBCONTRACTORS
8.1 Special attendance
The priced document shall make provision for the contractor to separately price for special attendance on each n/s subcontractor."
https://tinyurl.com/33t89d7u
"Additional requirements should be described as 'Special attendance'."
https://tinyurl.com/bnm3bkwv
"The Subcontractor will be responsible for all other attendances with exception of special attendance."
https://tinyurl.com/4e9rbnv5
"Special attendance is specific to a particular supplier or sub-contractor if it requests that it is provided by the main contractor."
https://tinyurl.com/8wmha6tv
"8.0 SPECIAL ATTENDANCE ON N/S SUBCONTRACTORS
8.1 Special attendance
The priced document shall make provision for the contractor to separately price for special attendance on each n/s subcontractor."
https://tinyurl.com/33t89d7u